Solar park Geertjesgolf
Near the villages of Deest and Winssen in Gelderland, Solinoor realised solar park Geertjesgolf: 4.2 MWp of green energy with more than 7,500 solar panels, built in just four months and fully operational since 21 December 2022. The energy generated is used directly by the sand extraction machines of NEDERZAND B.V., and the park is also connected to the electricity grid.
Project overview
Deest & Winssen, Gelderland
Direct supply for sand extraction
The energy from Geertjesgolf is used directly by the machines of NEDERZAND B.V. for sand extraction, supplemented by a grid connection. This makes sand extraction more energy-efficient, cost-effective and CO2-neutral. In this way, the project contributes to sustainable development and the reduction of CO2 emissions in the region.
A second life for an old landfill
What makes this project unique is its location: a former bulk waste landfill. This required an innovative design for the foundation and cabling, with techniques carefully tailored to the conditions of the underground. As a result, a piece of land that would otherwise go unused is now being used efficiently.
From contract to delivery in four months
The pace was high. After the contract was signed in July 2022, construction started in September with the specially designed concrete foundation. By early November, all 7,650 panels had been installed, in less than five days: a record of more than 1,500 panels per day. After the cabling and testing period, the park was fully operational on 21 December 2022.
Project phase & milestones